Carport Berlin-Spandau
Carport Berlin-Spandau
Operator:                        MW Solar Consulting GmbH
Energy company:          Vattenfall Europa AG
Location:                         Berlin-Spandau
Commissioning date:   December 2009
Completion period :      8 weeks
Rated system power:  998 KWp
Evo Bus
Evo Bus
Operator:                              SWU Energie GmbH
Energy company:                SWU Stadtwerke
Location:                               Neu-Ulm, Germany
Commissioning date:        12/23/2008 (phase 1) &
                                                03/05/2009 (phase 2)
Completion period:             5 months
Rated system power:        2,300 KWp
Sturm
Sturm
Operator:                                Wilhelm Sturm
Energy company:                  Stadtwerke Straubing
Location:                                 Salching, Germany
Commissioning date:           June 2007
Completion period:               10 weeks
Rated system power:           940 KWp
Ziegenaus
Ziegenaus
Operator:                            Sägewerk Anton Ziegenaus
Energy company:              E.ON Bayern AG
Location:                             Schiltberg
Commissioning date:      May 2006
Competion period:           4 weeks
Rated system power:     285 KWp
Schwaab
Schwaab
Operator:                               Karl Schwaab
Energy Company:                 LEW
Location:                                Langweid, Germany
Commissioning date:          June 2005
Completion period:              6 weeks
Rated system power:         259 KWp
Munich Trade Fair Centre
Munich Trade Fair Centre
Operator:                                   6 x Phoenix Solar Fonds
                                                     Verwaltung GmbH & Co.KG
Energy Company:                    Stadtwerke München
Location:                                   Munich/Riem, Germany
Commissioning date:            2002
Completion period:                 6 weeks
Rated system power:            1,058 KWp